Block: OverallStage: 3 Application of CCC in progress/issuance of vacant possession
Block: B8 Stage: 3 Application of CCC in progress/issuance of vacant possession
Block: B9 Stage: 3 Application of CCC in progress/issuance of vacant possession
Block: B10 Stage: 3 Application of CCC in progress/issuance of vacant possession
Block: B12 Stage: 3 Application of CCC in progress/issuance of vacant possession
Block : OVERALL Stage : 2g – The drain works completed, 2h – The road works completed
Block : B8 Stage : 2g – The drain works completed, 2h – The road works completed
Block : B9 Stage : 2g – The drain works completed, 2h – The road works completed
Block : B10 Stage : 2g – The drain works completed, 2h – The road works completed
Block : B12 Stage : 2g – The drain works completed, 2h – The road works completed
Overview of Suria 2a
Block B8 – Building finishing touch up works & main infra works in progress.
Block B9 – Building finishing touch up works & main infra works in progress .
Block B11 – Building finishing touch up works & main infra works in progress .
Block B7 – Building touch up works & main infra works in progress
Block B10 – Building touch up works & main infra works in progress
Block B11 – Building touch up works & main infra works in progress
Block B7 – Painting and touch up works in progress
Block B8 – Painting and touch up works in progress.
Block B11 – Painting & touch up works in progress
Block B7 – Internal & External Plastering works in progress
Block B9 – Undercoat Painting works in progress.
Block B11 - Undercoat Painting works in progress
Block B7 – Roofing works in progress
Block B8 – Brick works and roofing works in progress.
Block B9 - Plastering works in progress
Block B7 – Structure works completed
Block B8 – Roof beam in progress.
Block B9 - Brickworks in progress
Block B12 - First floor slab in progress.
Block B10 - Ground column works in progress
Block B8 – Ground beam works in progress